58 Regent Street Kogarah

Thirteen-level concrete structure over two basement levels in Kogarah.

A 13-level, two-basement formwork and concrete structure project delivered with HYZ at 58 Regent Street, Kogarah.

Concrete slab and reinforced walls under construction with formwork and site crew in a basement.
Client
HYZ
Builder
HYZ
Developer
HYZ
Location
58 Regent Street Kogarah
Region
Kogarah, NSW
Sector
Multi-residential
Category
Formwork, Concrete structures
Status
Completed
Started
21 March 2022
Completed
1 September 2022

The project

Project overview.

USS Formwork supported concrete structure delivery at 58 Regent Street, a single-building development comprising 13 levels and two basement levels. The photographed works show basement walls, core elements, slab formwork, stair construction and progressive concrete placement within the excavated site.

The challenge

The deep basement excavation and adjoining occupied properties required formwork, access and concrete works to be coordinated within a constrained urban site.

Our approach

Temporary support, deck formwork, vertical elements and stair construction were staged with reinforcement and concrete activities to support the structural sequence through the basement and upper levels.

The outcome

The project reached recorded completion in September 2022 after the basement and upper-level concrete structure works.

Our work

USS scope.

USS Formwork's scope covered formwork and concrete structure activities across the basement and upper levels, including slab decks, vertical elements, stairs, temporary support and coordination around reinforcement and concrete placement.

Services

  • Formwork
  • Concrete structures
  • Slabs and vertical elements
  • Commercial and multi-residential

Scope items

  • Basement slab formwork
  • Suspended slab formwork
  • Wall, column and core formwork
  • Stair formwork
  • Temporary propping and shoring

Formwork systems

Plywood deck formwork, Timber bearers and shoring, Vertical element formwork

Materials and systems

Reinforced concrete slabs, Reinforced concrete walls and cores, Reinforced concrete stairs

Project information

Key structural facts.

Single 13-level concrete structure with two basement levels and a source-recorded area of 27,251 m².

Levels
13
Basement levels
2
Buildings or towers
1
Source-recorded area
27,251 m²

Delivery update

Project progress.

Overall progress100%

Discuss your requirements

Planning an upcoming structure?

Talk to USS Formwork about the formwork and structural concrete requirements for your project.

Discuss your project